|
10 Truths About The New Home
Process
We know that your
satisfaction with your home purchase is the result of comparing your
expectations with the realities of the experience. To maximize your
satisfaction, we would like to call attention to several common areas of
confusion or misunderstanding. Our hope is to prevent surprises and assure
that you enjoy the new home process.
Time
The contract session, arranging financing,
making selections, visiting the site to meet with the builder,
orientation, closing, moving in, and warranty service – all require your
time. Several of these will necessitate your taking time off of work.
Pace of Work
Between your commitment to build and the
start of work, time is needed to finalize plans, arrange financing, obtain
engineering, apply for and receive a building permit, and schedule the initial
trades to begin work. These essential activities take several weeks to
accomplish.
Once work begins, several
construction stages – for instance, framing, drywall, interior and
exterior trim – proceed in spurts offset by slow periods. For instance, at
frame stage, the big walls go up quickly, while detailed work takes time
but makes less visual impact. Also, expect days when no one is working due
to such things as pending inspections or weather delays. These occur with
every home.
Questions
Avoid incomplete or inaccurate answers by
channeling all questions through our office. Field personnel, including
trades people, are unlikely to know all the factors that affect the answer
and can unintentionally give you wrong information.
Change Orders
When a new home is started, a momentum has
begun. We schedule some trades and materials weeks in
advance. The actual cost of a change may be minor compared to the cost of
confusion and mistakes that can occur when changes generate conflicting
instructions in the field. Avoid this by requesting any changes within the
schedule we outline.
Neighbor’s Homes
Speaking of changes, with today’s increased
flexibility, builders everywhere are accepting more custom changes. You
may see a great idea – in the home of a future neighbor. Even the most
talkative builder could not mention every conceivable change or
combination of features to their buyers. Shop thoroughly and think
carefully about what you want in your home. Your future neighbors will see
things in your new home they wish they had thought of, too.
Variations
Expect slight variations between the model
home you viewed and your home – even though the floor plan is the same.
A new home is like an oil painting. Even with the same view, same paints
and brushes, the artist creates a unique interpretation of the scene.
Similarly, no two homes are exactly the same. In addition other changes
may result because manufactures change models, codes are revised, or new
regulations go into affect.
Ugly Duckling Stages
Be prepared for the ugly duckling stages.
Construction of a new home occurs outdoors in all kinds of weather. Mud,
wind, dust, rain, and snow are part of the process.
Every home goes through a
couple of periods when it looks messy – such as the point where drywall
scraps are all over. Another seemingly chaotic stage occurs just prior to delivery
as dozens of details are adjusted and finalized. The intense activity of
so many trade and builder employees can make the most experienced buyer
nervous. The models you visit went through these same stages.
Perfection
Your new home is one of the few
hand-crafted products you purchase. Each home includes nature’s
fingerprint on the natural materials and the equally natural variations
that result when human beings rather than machines assemble the parts.
Unfamiliar Products
Learn about the performance and care of
familiar products. Nothing in a home is indestructible and each component
has individual needs. Avoid disappointments by becoming an expert on items
that may be unfamiliar such as marble, hardwood flooring, or fiberglass bath
fixtures.
Maintenance
A new home requires care from day one. This
care includes protecting its surfaces from damage, routine cleaning,
replacing consumable parts, lubricating and adjusting items that move, and
preventive maintenance. Review all the literature that comes with your
home and be aggressive in its care – it is your most important investment.
If you need additional information, contact our office for assistance.
|
The Building
Process
1. SLAB (Finished Floor)
Example Below is for
Post-Tension Slabs |
|
B. Excavate
footing/install rebar steel and pour concrete.

E. Place "fill
sand" inside the floor area.

G. Concrete is
then "poured" 4" thick in floor area and 18" thick over top of
footing.

|

A. The lot is
cleared and the building site is leveled (called pulling the
pad)

C. Build forms
for concrete slab.
D. All
underground Plumbing is installed (Water lines, sewer and
drains).

F. Install the
"post tension cables" per engineers / level and prepare the sand fill for
the concrete.

H. Stress the
"post tension" cables (this task is performed approximately 7 days after
the slab is poured). Each cable is tension stressed to 25,000
lbs.*
Note* Work can
still be performed on the slab during this curing period. |
|
|
2. Framing |
|

A. The lumber
package is delivered to the building site.

C. Install the
floor / ceiling joist.
D. Install the
roof rafters.

G. Install the
siding / cornish.
Note* Upon
completion of all rough-ins and prior to insulating, a city inspection is
made to ensure that all work has been done in accordance with the building
codes for each contractor.
|

B. Build and
raise the walls.

E. Install the
roof decking.
F. Install the
Windows.

H. Install the
roof shingles.
|
|
|
3. Sheetrock / Exterior Veneer /
Trim / Millwork. |
|

B. Install
overhead HVAC ducts.

D. Install
phone lines, security, computer, cable lines and any additional electrical
specialty wiring.

F. "Hang the
sheetrock".

H. Install the
brick / stone or other veneer material.
 |

A. Install
electrical wiring.

C. "Top out
the plumbing" / install roof vents.

E. Install
wall and batt insulation.

G. Finish and
prepare the wall for painting (tape and bed).

I. The
millwork is then delivered and installed by the trim carpenter (cabinets,
interior doors, baseboards, stair parts, closet shelving,
etc.).
|
|
|
4. Interior & Exterior Paint
Complete |
|

A. Stain and
or paint all cabinets.
B. Stain and
or paint all interior doors and millwork.
C. Paint all
interior doors.

E. Paint the
exterior.
F. Paint and
or stain all exterior door surfaces.
|

D. "Mask off"
all woodwork prior to painting the walls.

|
|
|
5. Final / Completion...Includes
all Landscaping. |
|

A. Install all
floor tile.

C. Install
furnaces and air conditioners...grills, registers &
thermostats.

E. Install all
light fixtures, appliances & complete the electrical.

G. Complete
all exterior door weather-stripping.

I. If specified,
install the landscape irrigation system.

L. Complete
security system.
M. Install any
remaining service systems (security, garage door operators,
etc.). 
O. The house
is then ready for one last walk through to make sure nothing has been
overlooked and everything is complete and satisfactory.
|

B. Install all
counter tops.

D. Install all
plumbing fixtures.

F. Install the
blown attic insulation.

H. Install all
remaining flooring (carpet/wood/vinyl).

J. Install the
grass (lay the sod).
K. Plant all
landscaping.

N. Install all
window screens.

|
|
|
Congratulations! Your Home Is Now
Finished.
Please note that this is a general overview
of the steps taken in the home building process. All builders
perform the procedures outlined above, however, individual builders may
vary the process to fit their preference and/or local building codes and
customs. Additionally, weather, material delays, and labor shortages
can alter the builders procedures and timing.
We hope this has been a helpful guideline
for you to follow when you build your new home. Please feel free to
contact us by phone, e-mail or in person with any questions you may have
about this section of our Web Site. |
|